Construction week 24 & 25: lots of snow shoveling
We had record snow fall in Ottawa last week. Apart from shoveling, here's a quick summary from the last couple weeks:
- roof sheathing, membrane, and metal roof
- truss blocking
- window bucks installed, reinforced and double-checked for size
- insulation started
Earlier today, Mark gave our first public tour of the house. We had around 15 people brave the construction site and cool temps to listen to how our house is coming together. Thanks to all who came out. Hope you learned something.
This upcoming week, Mark will finish insulating. And our windows are getting installed. EeK!!!