Construction weeks 10 & 11: foundation complete

Last I wrote, I left us on a cliffhanger, didn’t I? Wood and hammers and nails — oh my! 

Oh no.

I jumped the gun. Much prep was yet required before framing could begin in earnest. Those tasks included:

1. Glued the last few stacks foam to the outside of our basement walls

All that foam combined (R-4/inch) should have an R-value of 74. (Ontario Building Code requirements for a foundation are as low as R-12 on the walls only).

Last layers of foam held in place while glue sets.

Last layers of foam held in place while glue sets.

2. Installed the frost skirt

Because the bottom of our foundation isn’t quite deep enough to guarantee that it will be below the frost line on any given winter, we needed a frost skirt. (This is a standard detail for shallow foundations in Canadian construction). It’s a thin layer of foam installed horizontally around the permitter of the building at foundation depth. Typical frost penetration is around 4 feet in Ottawa, but last years' exceptionally cold winter brought that to 6’. A frost skirt is used on shallow foundations to extend the path that frost must travel to reach the bottom of a foundation. Bad news if it were to happen — expansion, contraction (heaving) leads to cracks and structural damage. 

Frost skirt and overlapping and waterproofing membrane.

Frost skirt and overlapping and waterproofing membrane.

3. Waterproofed the foundation

Using a Nudura waterproofing membrane, which is a peel-and-stick rubberized sheet. This required some patience because the foam had to be cleaned and dried prior to application. It wasn’t adhering as snugly as we’d have like to see, either. Some temporary strapping helped with this. A dimple board, held on place with metal fasteners, was layered over top of the membrane. Bam. Waterproofed.

4. Set up drainage

Water shall not pass (our membrane) and will weep if it dares to encroach. Weeping tile was placed around the perimeter of the foundation and connected to the storm sewer. There is a filter sock around it to prevent it from filling up with sand. (Am I the only one who finds the term weeping tile odd? There is no porcelain or ceramic whatsoever. It’s a plastic pipe with some nylon around it. Weeping tile does sound dramatic, however. I therefore think it sticks).

Dimple board and weeping tile.

Dimple board and weeping tile.

5. City inspection

Our city inspector wanted to check things out prior to back fill. So he paid a visit. He decided he wanted to throw in an additional check, which threw a bit of a wrench in to our coordination efforts (see next step).

6. Backfill

There were two steps to the backfill process. First we covered the drain tile with clean gravel (as to not clog the nylon with sand and silt straightaway). Cue city inspector – who gave us the thumbs up. And then we filled up the hole with native fill (some of which has been sitting around and taking up precious room on site and some that was stored off-site).

My oh my. What a difference this back fill has made. Now that half of the foundation walls lie underground, it actually looks and feels like a basement from the outside. 

Backfill stage 1: clean fill

Backfill stage 1: clean fill

Backfill stage 2: native fill

Backfill stage 2: native fill

7. Sill plate leveling and installation

This sill plate is what our first floor walls rest on. It’s a 2 x 6” piece of lumber that’s installed on top of the concrete, leveled with grout. 

sill-plate-ottawa-passivehouse

8. Ledger board and air barrier prep

The ledger board is what our first floor floor rests on. Remember those ledger bolts that were screwed into the concrete? These hold up the 2 x 10” ledger board. But out air barrier goes up first – Siga MAJPELL 5 membrane. Mark had a Periscope broadcast on this last week. They installed it with excess available to overlap once the second/main floor goes up. (Gotta keep that air barrier line as clean and streamlined as possible!)

Air barrier detail over ledger bolts

Air barrier detail over ledger bolts

Ledger board install

Ledger board install

And so forth

That’s the house up-to-date. Additionally, we had a few deliveries made and spent some time shuffling our construction materials around as we suddenly had a lot more room with the backfill out of the way. Our neighbours were no doubt pleased to regain their front lawn. And we lost a couple days due to bad (wet) weather.

Lotsa stuff out front. 

Lotsa stuff out front. 

Behind the scenes, there was a bit of good news. We applied for our first construction mortgage withdrawal. Mark explained our house build to the appraiser, and why our breakdowns/allotments should be different. The appraiser accepted Mark’s breakdowns — whoot! We have been reimbursed for Phase 1. Foundation complete. This helps alleviate some of our financial pressures.

For next week: wood and hammer and nails — oh my! 

Foundation Construction Details

Slab and foundation/basement walls with insulation and frost skirt

With the slab poured and the ICF well under way, I thought I would write a quick post with visuals explaining the construction methods and materials being used. I've created some images to go along with all the photos we've been posting to hopefully add some clarity to what you've been looking at so far!

The images above and below show the concrete foundation and foam insulation as it will be once completed. The image below has labels calling out the various layers. 

Components of the foundation

The biggest difference between our foundation and a typical residential foundation is the lack of concrete footings.  A typical foundation would pour strip concrete footings right onto undisturbed soil, then pour the concrete walls, and finally pour the slab inside the walls. In our home, the slab is poured before the walls and will actually support them, which is why it is so much thicker (8" instead of the standard 4") and has so much steel rebar in it. It is also completely contained within the foam insulation tray, eliminating any thermal bridging through the concrete to the ground. The end result of this is a concrete floor that will retain the heat it absorbs from the house above, rather than simply dumping it through into the ground. 

The walls on top of the slab are made up of three layers. First is the ICF (insulated concrete forms) from Nudura. These are like Lego for grow ups. They snap together to form the walls and are held apart by integrated webbing. The cavity is 6" wide and on Friday we will be pouring it full of concrete. Watch for photos this week showing the alignment system that will ensure the walls are straight and true as the concrete is poured. 

Once the concrete is poured and the walls straightened, we will be adding two more layers of foam from Styrorail to the exterior to build up the insulation value of the walls. The first layer has horizontal wood strapping embedded, and the second layer will cover this wood and effectively embed it in the middle of the wall. The foam will be glued in place using PL 300 glue, which is specifically formulated not to deteriorate the foam over time. The horizontal wood strapping gives us something to tie back into when we go to install our siding above grade. 

The slab poured and the first layer of ICF in place. 

Now let's talk about the big white elephant in the room: why so much foam? The amount of insulation is one of the trade offs required to achieve passive house performance on such a challenging site. Because of the limitations of orientation and south-facing window areas, we have to compensate by beefing up the thermal envelope more aggressively than you might find in other passive house projects. The final thickness was determined after several rounds of refinement of the energy model (using PHPP for those keeping track). The really nice thing about this configuration is that all of the concrete is on the warm side of the thermal envelope, where it will hold its warmth, and is protected from expansion and contraction. This alignment becomes especially important when we get to the design of the framed walls above...more on that soon. 

ICF at the end of 1 day's work.  

ICF at the end of 1 day's work.  

Construction week 8: the slab

passive-house-forms
passive-house-slab

Work started this week with more rebar — the critical metal mesh which reinforces our structural concrete slab. Once the metal work was complete, our structural engineer, Peter Campbell, came by to inspect and sign-off on it. Check and check. We were ready for concrete.

I am relieved to say that the concrete pour went really well. The team was great and the slab looks great. But this step did not want to happen. First of all, concrete is surprisingly expensive. We had a hard time assembling quotes. Ended up having our guys at Cornelis Grey tie and prepare the metal, ordering our concrete from one company, and a concrete pump truck from another company. A lot of extra coordination. And then on the day before the pour, our concrete team tried to cancel on us! Fortunately for us, Mark can be very persuasive and eventually it all worked out. Once underway, they had to pause work several times to clear leaves off the wet concrete, but otherwise all good.

On Friday, our Cornelis Grey team started installing the ICF forms for our basement walls. This work will spill over to next. And today we ventured out to the Herrmann's. We ordered our Gaulhofer windows and doors through them and they have been sitting in their immaculate warehouses for a couple months now. We finally found the time to visit them. Boy are they spectacular. And those blue doors! Swoon. They will be a joy to operate every day. Really looking forward to getting those installed. We’re still hoping to be closed in before Christmas.

This was a big week. We have a fab slab. Now it’s onwards and upwards — with walls! Speaking of those walls, I think it’s high time I get Mark to post a little something about them. There aren’t enough hours in the day. 

And some more pics from the week:

Concrete pour -- hand troweling near the wall rebar

Concrete pour -- hand troweling near the wall rebar

Machine leveling

Machine leveling

Site inspection

Site inspection

Our big blue door!

Our big blue door!

Insulated tray slab foundation

This is the insulated tray into which our structural concrete slab will be poured. This is the cosy foundation of our new home!

The last week has flown by as we've happily watched our house start to take shape. Last Wednesday we received our first insulation shipment from StyroRail. The first shipment of foam is for the insulated tray that will hold our structural slab. The foam is called SRP 400 and is a high density expanded polystyrene with a compressive strength of 40 PSI (aka strong enough to hold up our house). StyroRail shipped all of the pieces of the insulation tray cut to size, so aside from cutting holes to pass the plumbing through there was no cutting or waste on site!

Our tray insulation being delivered by StyroRail.

Before I get too far, I should explain what had to happen before the foam went into the hole. After installing the ground loop we backfilled with 6" of stonedust to protect the loop and create good contact with it. It was then time for the underground plumbing and electrical preps, which were very cleanly executed by Ackland Plumbing and Portage Electric. Then 12" of additional fill were laid in two lifts. Each time fill was added it was compacted to provide the bearing strength we need to support the house. The last pass levelled the gravel pad to within about an inch of level all over, simplifying the installation of the foam.

At last it was time for the foam. After laying the first few pieces we noticed that even though the gravel was nearly level there were still voids under some of the pieces. In order to get as close to perfection as possible we decided to use some extra stone dust to fill the voids and truly line up the foam blocks. It worked like a charm, and with only 2 days of work the team from Cornelis Grey had all the pieces in place, secured with straps and foam and gravel ballast.

Now that's a straight edge. Good job team!

Next steps are to install the frost skirt and drain tile around the perimeter of the tray, after which we will backfill over them to provide extra support to hold everything in place. We will then lay the 6 mil poly vapour barrier and rebar into the tray prior to pouring concrete early next week!
This stage has been really exciting to watch as I think it really showcases how smooth and clean the process can be when well planned. The whole team is doing a great job so far. I can already picture the concrete slab nestled nicely into its insulated tray, safe and warm and comfortable. The robustness of our building shell starts with this foundation, and it's off to a great start.